To complete your OPI install verification, simply submit the Agency Agreement Install Verification application along with the required installation photographs for evaluation. Once submitted, your OPI Success representative will review the application. They will provide feedback on any necessary changes that need to be made onsite. If everything is in order, your site will be verified, and the next steps for commission payment will be initiated. Here are some pictures and descriptions outlining the information OPI requires to certify you as an installer:

Agency Agreement Install Verification Application



  1. Gateway Installation: You need to submit a photograph of the Gateway Node installation site, demonstrating a clear line of sight view of the bins/cable node installation locations if possible.

  2. Gateway MAC Address & PIN: You need to submit a photograph of the Gateway Node with the MAC Address and PIN clearly visible.
    Gateway MAC

  3. Gateway Node Power Panel: You need to submit a photograph of the Gateway Power Panel Enclosure. The picture needs to demonstrate that the Gateway Node is connected to POE1, and the Internet Connection is connected to POE2, with the POE2 switch in the correct position.
  4. Cable Node Installation: 
    1. CN01: You need to submit a photograph of the CN01 installation, highlighting the wiring of the INT2 connection inside the CN01 node.
    2. CN08: You need to submit a photograph of the CN08 installation, highlighting the wiring of the INT2 connections into the CN08 CNE base inside the node.
  5. Cable Installation: You will need to submit a photograph of either the external or internal mount of the cables, highlighting the external bracket, angle of cable on angled roof, and Eye Bolt installation if cables are mounted internally.
  6. Weather Station Installation: You need to submit a photograph of the weather station installation location, showcasing that it is installed at the correct elevation, and that it is not installed too close to a body of water or the fan exhaust. 



  7. Fan Node Installation: You need to submit a photograph of the fan node panel, showcasing the wiring from each connected component into the Fan Node terminals.



  8. Plenum Sensor Installation: you need to submit a photograph of the PP0T installation, demonstrating that it is installed in the bin wall positioned where the plenum space is located between the plenum floor and ground floor. Additionally, the PP0T needs to be installed approximately 45 degrees away from the fan location.

 

Blue Lite Installs: These installs will not require as many pictures as the OPI Blue installs, but they do have some specific pieces of hardware that we would like to verify are installed correctly.

1. Cable Junction Enclosure (pictured) or 3 to 1 Splitter: Whatever the set up is for having multiple cables come together into a single read out point, we will need a photograph of the connection of the cables to verify that it is done correctly.

2. Docking Station: This will be at the bottom of the bin and be the single read out point for your customer's Blue Lite. Please highlight the drip loop and the read out point being installed into the INT2-DOCK-SHRT.

 